Pathfinder Mine Tonopah, NV

Manage project design for owner

  • NVE large generator interconnection process
    • Preliminary power flow model
  • Preliminary solar design
    • Fixed vs. single axis design optimization
    • PVsyst and SAM output modeling
    • Behind the meter integration
    • Optimize grading plan
    • Substation interconnection
  • Preliminary storage design
    • AC vs. DC system coupled considerations
    • Optimize AC/DC inverter ratio and GCR

Status

  • Large generator interconnection submitted to NVE 2022 spring queue
  • System impact study showed unfinanceable upgrade costs.  The project has been shelved until NVE upgrades are in place.